COGIS - COA/BMP Information

HIGHPOINT OPERATING CORPORATION           Fox Creek 12-63-36-1-1N           Well API # 05-123-50472           Status: XX        Status Date: 08/24/2019           Location ID #:466980       SWSW 25 12N 63W WELD

COGIS - Conditions of Approval
COA Search Results - 2 record(s) returned.
Source
Document
Conditions of Approval
Form: (02 )
401887171
08/24/2019
1) Submit Form 42 online to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad. 2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log. Bradenhead Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test.: 1) All: Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation. 2) Delayed completion: 6 months after rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation. 3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance.
Form: (02 )
401887171
08/24/2019
Operator will ensure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed.


COGIS - Best Management Practices
BMPSearch Results - 2 record(s) returned.
Source
Document
BMP TypeBMP
Form: (02 )
401887171
08/24/2019
Drilling/Completion Operations
HighPoint will adhere to the COGCC Policy for Bradenhead Monitoring effective 5/29/12.
Form: (02 )
401887171
08/24/2019
Drilling/Completion Operations
Multi Well Open-Hole Logging – Rule 317.p: Alternative Logging Program: One of the first wells drilled on the pad will be logged with open-hole resistivity log and gamma-ray log from the kick-off point into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured-while-drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run and have those logs attached. The Form 5 for a well without open-hole logs shall state “Alternative Logging Program -No open-hole logs were run” and shall clearly identify the type of log and the well (by API#) in which open-hole logs were run.