   NOBLE ENERGY INC    C33-14 Pad   LOCATION#: 459550   Status:AC as of 12/5/2018 12:17:25 PM   SESW 33 4N 64W WELD COUNTY
Search Results - 2 record(s) returned.
Type Source Conditions of Approval
Best Management Practices
OGLA
02A
401795635
11/8/2018
The Approved Form 2A permit will be posted at the location during construction, drilling, and completions operations.

OGLA
02A
401795635
11/2/2018
This Form 2A and related Form 2s are approved subject to the Noble Mustang CDP accepted by Commission Order # 1-228.

COGIS - Best Management Practices COGIS - Best Management Practices Results

Search Results - 5 record(s) returned.
BMP TypeSource BMP
Dust control
02A
401795635
10/31/2018
Noble shall employ practices for control of fugitive dust caused by their operations. Such practices shall include but are not limited to the use of speed restrictions, regular road maintenance, restriction of construction activity during high- wind days, and silica dust controls when handling sand used in hydraulic fracturing operations. Additional management practices such as road surfacing, wind breaks and barriers, or automation of wells to reduce truck traffic may also be used if technologically feasible and economically reasonable to minimize fugitive dust emissions.
Emissions mitigation
02A
401795635
10/31/2018
The operator shall employ sand traps, surge vessels, separators, and tanks during flowback and cleanout operations to safely maximize resource recovery and minimize releases to accommodate green completions techniques. Operator will use an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. When commercial quantities of salable quality gas are achieved at each well, the gas shall be immediately directed to the sales line or wells will be shutin and gas conserved. If a sales line is unavailable or other conditions prevent placing the gas into a sales line, the operator shall not produce the wells without an approved variance per Rule 805.b.(3)C. The Rule 912 notice and approval requirements apply regardless of a variance from Rule 805.b.(3)C.
General Housekeeping
02A
401795635
10/31/2018
Housekeeping will consist of neat and orderly storage of materials and fluids. Wastes will be temporarily stored in sealed containers and regularly collected and disposed of at offsite, suitable facilities. If spills occur prompt cleanup is required to minimize any commingling of waste materials with stormwater runoff. Routine maintenance will be limited to fueling and lubrication of equipment. Drip pans will be used during routine fueling and maintenance to contain spills or leaks. Any waste product from maintenance will be containerized and transported offsite for disposal or recycling. There will be no major equipment overhauls conducted onsite. Equipment will be transported offsite for major overhauls. Cleanup of trash and discarded materials will be conducted at the end of each work day. Cleanup will consist of patrolling the roadway, access areas, and other work areas to pickup trash, scrap debris, other discarded materials, and any contaminated soil. These materials will be disposed of properly.
Planning
02A
401795635
10/31/2018
Lighting on well pad locations is considered temporary and will be used during drilling, completion and construction activities. Temporary lighting will be directed downward, inward, and shielded towards location to avoid glare on public roads and building units within 1,000 feet. Lighting will be turned off when practical, i.e., no operations being conducted.
Storm Water/Erosion Control
02A
401795635
10/31/2018
Stormwater BMP’s will be constructed around the perimeter of the site prior to, or at the beginning of construction. Specific BMP’s used may include stockpile stabilization, grading, sediment traps, and perimeter barriers based on final construction design and will remain in place until the pad reaches final reclamation.