COGIS - COA/BMP Information

ENERPLUS RESOURCES (USA) CORPORATION           Dante 8-66-34-33N           Well API # 05-123-50137           Status: XX        Status Date: 04/16/2019           Location ID #:453481       SESE 34 8N 66W WELD

COGIS - Conditions of Approval
COA Search Results - 2 record(s) returned.
Source
Document
Conditions of Approval
Form: (02 )
401606111
04/16/2019
1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU for the first well activity with a rig on the pad and provide 48 hour spud notice for each subsequent well drilled on the pad. 2) Comply with Rule 317.j and provide cement coverage from TD to a minimum of 200' above the Niobrara. Verify coverage with cement bond log. 3) Oil-based drilling fluid is to be used only after all aquifers are covered.
Form: (02 )
401606111
04/16/2019
Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test: 1) Within 60 days of rig release and prior to stimulation or 2) If a delayed completion, 6-7 months after rig release and prior to stimulation. 3) Within 30 days after first production, as reported on Form 5A.


COGIS - Best Management Practices
BMPSearch Results - 5 record(s) returned.
Source
Document
BMP TypeBMP
Form: (02 )
401606111
04/16/2019
Material Handling and Spill Prevention
Implement a Spill Prevention Control and Countermeasures (SPCC) to prevent and address any releases from bulk oil storage located onsite.
Form: (02 )
401606111
04/16/2019
Dust control
Operator shall employ practices for control of fugitive dust caused by their operations. Such practices shall include but are not limited to the use of speed restrictions, regular road maintenance, restriction of construction activity during high- wind days, and silica dust controls when handling sand used in hydraulic fracturing operations. Additional management practices such as road surfacing, wind breaks and barriers may be used.
Form: (02 )
401606111
04/16/2019
Emissions mitigation
Associated Gas Flaring BMP -Following the last stage of separation associated gas will flow through a liquid knockout drum to remove entrained liquid phases. Following the liquid knockout drum, associated gas will flow to a smokeless combustion device capable of a 98% control efficiency. The combustion device will be equipped with a continuous pilot gas flame and an auto-igniter. Enerplus will comply with all applicable Colorado-Air Pollution Control Division requirements to ensure adequate design and operation of the control device is maintained.
Form: (02 )
401606111
04/16/2019
Odor mitigation
Oil & gas facilities and equipment shall li>e operated in such a manner that odors and dust do not constitute a nuisance or hazard to public welfare.
Form: (02 )
401606111
04/16/2019
Drilling/Completion Operations
One of the first wells drilled on the pad will be logged with Cased hole Pulsed Neutron Log with Gamma Ray Log from the kick-off point to into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured while-drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run in that well and have those logs attached. The Form 5 for each well shall clearly state "No open- hole logs were run" and shall reference the Rule 317.p Exception granted for the well.