COGIS - COA/BMP Information

KP KAUFFMAN COMPANY INC           JOHNSTON ET AL 20-1           Well API # 05-123-12214           Status: PR        Status Date: 04/01/2019           Location ID #:322884       NESE 20 1N 65W WELD

COGIS - Conditions of Approval
COA Search Results - 4 record(s) returned.
Source
Document
Conditions of Approval
Form: (04 )
401604288
07/02/2018
Bradenhead tests shall be performed according to the following schedule and the Form 17 submitted within 10 days of each test: 1. Within 60 days prior to recompletion 2. Within 60 days after recompletion
Form: (04 )
401604288
07/02/2018
Recomplete cannot be performed without an approved Form 2. 1) Prior to recomplete provide remedial cement to isolate the aquifer from 1261’ to at least 50’ above the surface casing shoe. Verify cement with a CBL and document with a Form 5. 2) Completed Interval Report, Form 5A, shall be submitted within 30 days after Recompletion.
Form: (02 )
401554364
07/03/2018
Bradenhead tests shall be performed according to the following schedule and the Form 17 submitted within 10 days of each test: 1. Within 60 days prior to adding cement and recompletion 2. Within 60 days after recompletion
Form: (02 )
401554364
07/03/2018
1) Prior to recomplete provide remedial cement to isolate the aquifer from 1261’ to at least 50’ above the surface casing shoe. Verify cement with a CBL and document with a Form 5. 2) Completed Interval Report, Form 5A, shall be submitted within 30 days after Recompletion.


COGIS - Best Management Practices
BMPSearch Results - No Records Found
Source
Document
BMP TypeBMP